Greenford High School – Off-site solution saves 10 weeks

Lady Margaret Road, Southall

Customer
London Borough of Ealing
Architect
Bond Bryan
Value
£9.7
Location
Lady Margaret Road, Southall

The change to Innovare’s structural insulated panel (iSIP) system saved 10 weeks on a traditional build and delivered £90k efficiencies to safeguard the budget.

Ealing Borough Council were delighted with performance and the project won the 2019 Constructing Excellence ‘Outstanding Customer Satisfaction’ Award.

“The construction went about as well as the school could possibly have asked for. The school think that the scheme is fantastic. Congratulations and thanks for your collective effort and hard work on the project. What a great result, you should all be very proud of yourselves. Thanks and gratitude to the wider Osborne team (including pre-construction and design) along with your supply chain in delivering this project to Practical Completion with such great results.”
Mathew Cramer, Head of Greenford High School, Ealing